Congress and Exhibition Syngas Nitrogen Uzbekistan and CIS is the only professional international platform for the leading companies of the methane gas chemical industry in Uzbekistan and CIS with the participation of the largest syngas processors, regulatory and supervisory authorities, licensors of production technologies, developers, producers and suppliers of equipment, engineering and design and construction companies, suppliers of technologies and services. The event is designed to discuss the largest investment projects for the construction and modernisation of production facilities, as well as the opportunities to improve the efficiency of existing companies-producers of nitrogen, methanol, ammonia, and mineral fertilisers (nitrogen, potash, phosphate, complex).
Construction of a nitric acid plant and an ammonia and carbamide plant
Operator/initiator: Navoiyazot
Location: Navoi region, Uzbekistan
Stage: –
Timeframe: 2023 - 2028
Investment volume: $1.5 billion
Realisation of the projects worth $1.5 billion will triple Navoiyazot annual output from $150 million to $410 million. The first plant will produce 500,000 tonnes of ammonia and 600,000 tonnes of carbamide per annum. At the same time, energy consumption to produce 1 tonne of ammonia will be reduced by 2.5 times. The second plant will produce 500,000 tonnes of nitric acid per annum and reduce electricity consumption by 18 times. These two projects alone will reduce the cost of nitrogen fertilisers by 30%.
Construction of Karakulkimyo ammonia and carbamide production plant
Operator/initiator: Casale SA / Ferkensco Management
Limited
Location: Bukhara region, Uzbekistan
Stage: –
Timeframe: 2025
Investment volume: $500 million
On 24 March 2022, Uzbek companies Ferkensco Management Limited, Enter Engineering Pte. Ltd. And Switzerland's Casale SA signed a co-operation agreement for the construction of a state-of-the-art ammonia-based fertiliser plant. Upon completion, the plant will produce 1,500 tonnes per day of ammonia and 1,800 tonnes per day of granular carbamide. Construction is expected to be completed in the first half of 2025.
Modernisation and expansion of existing facilities (ammonia, carbamide, ammonium nitrate, nitric acid)
Operator/initiator: Farg'onaazot
Location: Fergana region, Uzbekistan
Stage: –
Timeframe: 2021 - 2025
Investment volume: $237 million
Annual capacity of the project: increase of ammonia capacity up to 660,000 tonnes, carbamide up to 600,000 tonnes per annum, ammonium nitrate up to 700,000 tonnes and nitric acid up to 560,000 tonnes per annum. Sources of financing: direct foreign investments as investment commitments of the investor during realisation of the main share in the authorised capital of Farg'onaazot JSC. Project benefits: reduced energy consumption and emissions, increased safety of production facilities.
Construction of a chemical complex on the production of complex mineral fertilisers
Operator/initiator: Samarkandkimyo / Ferkensco Management Limited
Location: Samarkand region, Uzbekistan
Stage: 2023 - design and general construction works are fully completed, acceptance and installation of process equipment and steel structures is in progress
Timeframe: 2020 - 2024
Investment volume: $200 million
On the territory of Samarkandkimyo JSC, Ferkensco Management Limited is realising an investment project on the production of complex mineral fertilisers in the volume of 910,000 tonnes per annum, including 370,000 tonnes of MAP and 540,000 tonnes of NPK.
Construction of green hydrogen fertiliser production facility
Operator/initiator: ACWA Power / Uzkimyosanoat
Location: Chirchik, Uzbekistan
Stage: 2023 - start of construction
Timeframe: 2025
Investment volume: $88 million
The project will be realised in two phases. It is expected that the production capacity at the first phase will be 3,000 tonnes per annum of green hydrogen with subsequent processing into mineral fertilisers. Upon completion of the second phase, wind power plants (WPPs) with a capacity of 2.4 GW will produce 500,000 tonnes per annum of green ammonia. As a result of efficient use of alternative energy resources, production of mineral fertilisers from green hydrogen and orientation of high value-added products to global markets will be one of the first in the world.
Construction of a methanol plant
Operator/initiator: MTO GCC
Location: Bukhara region, Uzbekistan
Stage: 2023 - preparation of the construction site
Timeframe: 2025
Investment volume: –
The 15-hectare facility, known as Methanol Island, is a key component of the MTO-based Gas-to-Chemicals Complex and will include a 1.3 million tonnes per annum synthesis gas methanol plant and an air separation plant that will produce oxygen and nitrogen for industrial needs. The planned commissioning date is 2025 and the expected operational life is 25 years.
First Deputy Chairman of the Board
Uzkimyosanoat
Chairman of the Board
MAXAM-CHIRCHIQ
Chairman of the Board
Samruk-Kazyna Ondeu LLP
First Deputy General Director - Chief Engineer
Grodno Azot
Project Director
Indorama Fertilisers (Eurasia)
Director, Gas Chemicals Department
Irkutsk Oil Company
Technical Director
Metafrax Chemicals
Deputy Director
Ifoda Agro Kimyo Himoya JV LLC
Head of Resident Relations Department
Chirchik Chemical Industrial Technopark
Head of Development Department
EuroChem
200+ leaders of the methane gas-to-chemicals industry in Uzbekistan and CIS with participation of the largest synthesis gas processors, authorities, investors and technology leaders
15+ investment projects on construction and modernisation of production facilities, as well as opportunities to improve the efficiency of existing nitrogen, methanol, ammonia and mineral fertilisers (nitrogen, potash, phosphate, and complex ones) producers in Uzbekistan
Current reality of the synthesis gas processing industry in Uzbekistan and CIS: progress and new perspectives
Achievements of technology industry leaders: market overview of technologies, equipment, solutions, and services
Methanol and ammonia: room for development. Planned and ongoing industry construction projects in Uzbekistan and CIS
25+ presentations from industry leaders: project managers, regulators, industry experts
New in the programme! Businesses' internal infrastructure: process efficiency, supply chain development, production problem solving, methods and forms of product realisation
Relevant! Technological development of the industry: best practices in innovations integration into production - practical examples
Nitrogen and mineral fertilisers: status of existing and future construction projects in Uzbekistan and CIS
Progressive modernisation: real effect of modernisation programmes at the industry - experience of ammonia, mineral fertilisers and methanol producers
30+ hours of business and informal networking: one-on-one meetings on a pre-arranged schedule, business lunches, coffee breaks, interactive discussions, and more
Cocktail Reception to make new acquaintances and strengthen existing business ties in an informal setting